Supreme Court of India (Division Bench (DB)- Two Judge)

Appeal (Civil), 6568 of 2016, Judgment Date: Jul 20, 2016


                                                              Non-Reportable


                        IN THE SUPREME COURT OF INDIA

                        CIVIL APPELLATE JURISDICTION


                       CIVIL APPEAL NO. 6568  OF 2016

                   (Arising out of SLP (C) No.17475/2008)


ELECTRICAL MFG. CO. LTD.                                 … APPELLANT


                                   VERSUS


POWER GRID CORPN. OF INDIA LTD. & ANR                  … RESPONDENTS


                               J U D G M E N T

Uday Umesh Lalit.J


Leave granted.


This appeal is directed against the  judgment  and  order  dated  04.07.2008
passed by the Division Bench of the High Court of Delhi  allowing  FAO  (OS)
No.196/2006, setting aside the judgment and order  dated  10.02.2006  passed
by the Single Judge of the High Court of Delhi in CS(OS) No.1201 of 1993.


A Contract for “400 KV Transmission Line Power Package for Rihand  –  Kanpur
– Eta – Kanpur Line” was  awarded  by  National  Thermal  Power  Corporation
(hereinafter referred to as “NTPC”) to the appellant herein.  Clause  26  of
the Contract titled  “Arbitration”  was to the following effect:-


“26.0 ARBITRATION

  26.1      If any dispute or difference of any kind whatsoever shall  arise
between the Owner and the Contractor, arising out of the  Contract  for  the
performance of the Works whether during the progress of the Works  or  after
its completion or whether before or after the  termination,  abandonment  or
breach of the Contract, it shall, in the first place,  be  referred  to  and
settled by the Engineer, who, within a period  of  thirty  (30)  days  after
being requested by either party to do so, shall give written notice  of  his
decision to the Owner and the Contractor.

  26.2 Save as hereinafter provided,  such  decision  in  respect  of  every
matter so referred shall  be  final  and  binding  upon  the  parties  until
completion of the Works and shall  forthwith  be  given  effect  to  by  the
Contractor who shall proceed with the Works with all due diligence,  whether
he or the Owner requires arbitration as hereinafter provided or not.

  26.3      If after the Engineer has given written notice of  his  decision
to the parties, no claim to arbitration has  been  communicated  to  him  by
either party within thirty (30) days from the receipt of  such  notice,  the
said decision shall become final and binding on the parties.

  26.4      In the event of the Engineer failing to notify his  decision  as
aforesaid within thirty (30) days after being requested as aforesaid, or  in
the event of either the Owner or the Contractor being dissatisfied with  any
such decision, or within thirty (30) days after  the  expiry  of  the  first
mentioned period of thirty (30) days, as the case may be, either  party  may
required  that  the  matters  in  dispute  be  referred  to  arbitration  as
hereinafter provided.

  26.5      All disputes or differences in respect of  which  the  decision,
if any, of the Engineer has not become final or binding as aforesaid,  shall
be settled by arbitration in the manner hereinafter provided.

  26.6.1 The arbitration shall be conducted by three arbitrators,  one  each
to be nominated by the Contractor and the Owner and the third  to  be  named
by the President of the Institution of Engineers, India.  If either  of  the
parties fails to  appoint  its  arbitrator  within  sixty  (60)  days  after
receipt of a notice from the other party invoking  the  Arbitration  Clause,
the President of the Institution of Engineers, India, shall have  the  power
at the request of either of the  parties,  to  appoint  the  arbitrator.   A
certified copy of the said President making such  an  appointment  shall  be
furnished to both the parties.

26.6.2 The arbitration shall be conducted in accordance with the  provisions
of the Indian Arbitration Act, 1940 or any statutory  modification  thereof.
The venue of arbitration shall be New Delhi, India.

  26.7 The decision of the majority of the arbitrators shall  be  final  and
binding upon the parties.  The expenses of the arbitration shall be paid  as
may be determined by the arbitrators.  The arbitrators  may,  from  time  to
time, with the consent of all the parties enlarge the time  for  making  the
award.  In the event of any of the aforesaid arbitrators dying,  neglecting,
resigning or being unable to act for any reason, it will be lawful  for  the
party concerned to nominate another arbitrator  in  place  of  the  outgoing
arbitrator.

  26.8 The arbitrator shall have full powers to  review  and/or  revise  any
decision, opinion, directions, certification or valuation of  the  Engineers
in consonance with the Contract, and neither party shall be limited  in  the
proceedings before such arbitrators to the evidence or arguments put  before
the Engineer for the purpose of obtaining the said decision.

  26.9 No decision given by the Engineer in accordance with  the  aforegoing
provisions shall disqualify him as being  called  as  a  witness  or  giving
evidence before the arbitrators on any matter  whatsoever  relevant  to  the
dispute or difference referred to the arbitrators as aforesaid.”


The Contract was completed and the aforesaid line was taken  over  by  NTPC.
In  respect  of  certain  claims  and  issues  raised  by   the   appellant,
negotiations took place and thereafter a Committee constituted  to  consider
the claims by its report dated 03.01.1991 recommended that claim in  respect
of Rs.10.35 lakhs could be accepted, provided the appellant  confirmed  that
there were no further claims. The appellant  thereafter  vide  letter  dated
18.07.1991 addressed to the Executive Director (NR), National Thermal  Power
Corporation Ltd., Indira Bhawan, Civil Lines, Allahabad, sought decision  in
respect of  pending disputes/matters.  It was stated that  the  decision  in
respect of issues so raised be conveyed to the appellant within 30  days  of
the date of the letter.  It appears that  by  letter  dated  14.08.1991  the
appellant was informed  that  “Engineer”  in  respect  of  the  Contract  in
question was General Manager (TL-NR) and that the  letter  dated  18.07.1991
was forwarded to him.  Soon thereafter i.e.,  on  02.09.1991  the  appellant
wrote to General Manager (TL-NR), National Thermal Power  Corporation  Ltd.,
Indira Bhawan, Civil  Lines,  Allahabad  that  the  aforesaid  letter  dated
18.07.1991 having been forwarded to him as “Engineer” of  the  Contract,  in
accordance with Clause 27 of the Contract  required  notice  was  deemed  to
have been served and that the appellant was waiting  for  reply  in  return.
However, nothing was heard within 30 days.


On 28.11.1991 NTPC wrote to the appellant that under the directions  of  the
Government of India, NTPC and National Power Transmission  Corporation  Ltd.
(“NPTC”, for  short)  had  entered  into  an  agreement  on  13.08.1991  for
management  of  construction,  operation  and  maintenance  of  Transmission
System  and  assorted  facilities  of  NTPC,  pending  completion  of  legal
formalities for transfer of ownership of the Transmission System to NPTC  in
due course of time. It was further stated that  NPTC  would  administer  the
Contract for and on  behalf  of  NTPC  and  all  further  correspondence  be
addressed to NPTC.


Though letters issued on 18.07.1991 and 02.09.1991 were admittedly  received
by NTPC which requested the Engineer to act in terms of the relevant  Clause
of the Contract, no action was taken in that behalf.   Even  after  issuance
of letter dated 28.11.1991, for next more  than  three  months  nothing  was
done either  by  NTPC  or  NPTC.   Therefore,  by  letter  dated  20.03.1992
addressed to NTPC the appellant informed that in as much as  the  “Engineer”
had failed to notify his decision within the period specified as per  Clause
26.4 of the Contract, the  appellant  was  invoking  Clause  26.6.1  of  the
Contract  regarding  arbitration  and  nominating  Shri  J.C.  Jain  as  its
Arbitrator.  The appellant requested NTPC  to  appoint  its  Arbitrator  and
give intimation to the President of the Institution of Engineer  (India)  in
order to enable appointment of the third  Arbitrator  so  that  adjudication
proceedings could be proceeded with. A copy of this letter was forwarded  to
and received by NPTC.  However, nothing was done for next  more  than  three
months.


On 7.07.1992,   the  appellant  wrote  to  the   President,  Institution  of
Engineers (India) drawing his attention to the letter  dated 20.03.1992  and
stated that despite being called upon to  appoint  an  Arbitrator  on  their
behalf within the period specified,  there was complete failure on the  part
of  NTPC.  Since the prescribed period of 60 days  had  expired,  a  request
was made vide said letter to appoint an Arbitrator and that a copy  of  such
appointment be furnished to both the parties and further steps be  taken  in
the matter. A copy of this letter was sent  to  the  Chairman  and  Managing
Director of NTPC.  On 24.08.1992 a telegram was sent by  Sr.  Manager  (P&C)
of NPTC to the President,  Institution of Engineers(India) to the  following
effect:-

                                “MESSAGE FORM

TO

PRESIDENT INSTITUTION OF ENGINEERS(INDIA)

8-GOKHLE  ROAD, CALCUTTA-700 020.


KINDLY REFER LETTER  NO.  HC/009/1-1  DTD.  7TH  JULY,  ’92  FROM  M/S  EMC,
REGARDING APPOINTMENT OF ARBITRATOR FOR DISPUTES  ARISING  OUT  OF  CONTRACT
NO. 01/00-75/177/-al, DTD.7.12.84 FOR  KANPUR-ETAH  TL  (.)  REQUEST  ACTION
REGARDING APPOINTMENT OF ARBITRATOR ON BEHALF OF RESPONDENT  BY  INSTITUTION
OF ENGINEERS MAY BE KEPT IN ABEYANCE(.) DETAIL LETTER FOLLOWS(.) REGARDS(.)


                                                                 (P.N.GUPTA)

                                                            SR. MANAGER(P&C)


Confirmation copy by post to:                SIGNATURE (of person   By
REGD. POST                         authorized to approve)


President Institution of                 NAME:P.N.GUPTA

Engineers(India), 8, Ghokhle        DESGN.: SR.MANAGER

Road, Calcutta- 700 029               DEPTT. P&C

M/s EMC Stealal Ltd.,

51, Catnal East Road

Calcutta                       CHECKED FOR DESPATCH

Shri V.L. Dua, S M (C)

N.D.

4.  Shri Gurman Singh,

     C.L.D. CC.N.D.

                                                  Dt. 24.08.92

 Regd. Office:  Hemkunt Chambers, 10th Floor, 89, Nehru Place, New Delhi-110
                 019 (Tel. 646 3390 91-92 Grams:‘ NATGRID’”


Since there was no follow up action and nothing was done  for  more  than  a
month, the Institution of Engineers (India) on 29.09.1992  appointed    Shri
P.P.Agrawal,  Chief  Consulting  Engineer,  Water  and   Power   Consultancy
Services (India) Ltd. as the Second Arbitrator in  terms  of  the  Contract.
On the same date Shri Som Gupta, Fellow  of  Institution  of  Engineers  was
appointed as the Third Arbitrator in the matter.  Intimation in that  behalf
was sent by letter dated 29.09.1992 to the Chairman and  Managing  Director,
NTPC.



On 08.01.1993, the “National Thermal Power Corporation Ltd,  National  Hydro
Electric Corporation Ltd. and the North-Eastern Electric  Power  Corporation
Ltd.  (Acquisition  and Transfer of Power Transmission Systems)   Ordinance,
1993” (No.10/1993) was promulgated  by  the  President  of  India.   As  per
Section 3 of the Ordinance, the Power Transmission  System  and  the  right,
title and interest of these three  companies  in  relation  to  their  power
transmission  systems  stood  transferred  to  and  vested  in  the  Central
Government  on  and  with  effect  from  the  appointed   day.   The   power
transmission  system  so  vested  in  the  Central  Government,  immediately
thereafter was deemed to have been transferred to and vested  in  the  Power
Grid Corporation India Ltd., i.e. respondent No.1  herein.    The  appointed
day under the Ordinance was 1st April, 1992.


On 13.01.1993, first meeting of the Arbitral Tribunal  consisting  of  three
Arbitrators, namely, Shri J.C. Jain, nominated by the appellant,  Shri  P.P.
Agrawal, nominated as the Second Arbitrator by  the  President,  Institution
of Engineers (India) and Shri Om Gupta, nominated as  the  Third  Arbitrator
by the President, Institution of Engineers (India) was held.   The  Arbitral
Tribunal entered upon reference in respect of the dispute  in  question.  It
was decided in this meeting to hold  the  next  meeting  on  11.02.1993  and
copies of the minutes of this meeting were forwarded to  the  appellant  and
the Chairman and Managing Director, NTPC.


On 04.02.1993, a letter was written by  respondent  No.1  to  the  appellant
that in terms of Clause 26 of the Contract,  arbitration  could  be  invoked
only if there was failure to settle the dispute amicably and this being pre-
condition of the contract, the matter was not  mature  for  arbitration  and
any step in that behalf would be in violation of the Contract.   A  copy  of
this letter was marked to the President, Institution of Engineers (India).


On 06.02.1993, the appellant filed its Statement of  Claim  in  the  sum  of
Rs.3.98 crores before the Arbitral Tribunal. On  11.02.1993  second  meeting
of the Arbitral Tribunal was held.  The  representative  of   the  appellant
brought the aforesaid Ordinance to the notice of  the Arbitral Tribunal  and
submitted that in view of the Ordinance,  respondent No.1 be  made party  to
the proceedings.  The Statement of Claim along with annexures  and  copy  of
the Contract were taken on record and the appellant was directed  to  supply
copies of the Statement of Claim to both NTPC  and  respondent  No.1.   NTPC
was directed to submit their reply to the statement of claim  by  04.03.1993
and all parties, namely,  the  appellant,  NTPC  and  respondent  No.1  were
requested to attend the next meeting of  the  Arbitral  Tribunal  which  was
fixed on 25.03.1993.  Copies of the minutes of this meeting  were  forwarded
to NTPC as well as respondent No.1. On 23.02.1993, a letter was  written  on
behalf of NTPC with copies to  the  Arbitrators  and  respondent  No.1  that
after promulgation of the aforesaid Ordinance, NTPC had  nothing  to  do  in
the matter.  Copy of the minutes of the  meeting  dated  11.02.1993  of  the
Arbitral Tribunal was forwarded  by NTPC to respondent No.1 along with  copy
of this letter dated 23.02.1993.


As the date fixed for the  next  meeting,  i.e.,  25.03.1993  was  a  public
holiday, a telegram was sent by the appellant  to  the  Arbitrators  and  to
respondent No.1 that the meeting be adjourned. On  12.03.1993  the  Convener
Arbitrator sent telegram to the appellant  and  respondent  No.1  confirming
the adjournment of the case to 05.04.1993.  On 20.03.1993  another  telegram
was sent by the Convener Arbitrator to the appellant and to respondent  No.1
that the date of hearing was shifted to 07.04.1993.


On 07.04.1993 third meeting of the Arbitral Tribunal was  held.  Though  the
appellant was present, respondent No.1 was absent.  It was  noted  that  the
minutes of the second meeting held on  11.02.1993  were  sent  to  NTPC  and
respondent No.1 and were received by them.   The  relevant  portion  of  the
minutes of the meeting dated 07.04.1993 was as under:


“It was also noted the minutes of the second meeting held on 11.02.1993  had
been sent both to M/s NTPC and M/s PGCIL and received by them.


      It was however noted with regret that no representative  of  M/s  NTPC
and/or M/s PGCIL turned up for the hearing.


      No compliance was  made  by  the  aforesaid  two  respondents  to  the
directive given to  them  in  the  second  meeting  regarding  filing  their
replies to the statement of claim filed by M/s EMC.


      During the third meeting Mr. M.K. Kureshi of M/s  EMC  requested  that
despite no response from respondents, the case should be proceeded with  and
the arbitrators were requested to deliver the  award  within  the  statutory
period of 4 months which expired on 12th May, 1993.


      Under the circumstances, it was decided that the next hearing  in  the
matter will commence from 10.30 a.m. on 20.04.1993 and continue on  all  the
days upto 25th April, 1993.  Each day the meeting shall commence from  10.30
a.m. and continue during the day in an effort to complete the items  on  the
agenda as specified in the following para.


      In the  meantime   respondents  are  again  requested  to  file  their
replies to the statement of claim filed by  the  claimants  and  such  other
documents that they may like to file before the Arbitrators by  14th  April,
1993 giving copies to all the three arbitrators and the claimants.


      M/s EMC are also requested to file such other documents that they  may
like  to  present  to  the  arbitrators  by  14.04.1993  giving  copies   to
respondents.


      Following matters will be taken  up  during  the  hearings  from  20th
April, 1993 upto 25th April, 1993:


Framing of the issues.

Admission/Denial of documents filed and taking the same on record.

Evidences by the claimants and respondents.

Arguments by claimants; counter arguments by  respondents;  replies  by  the
claimants.”



On 09.04.1993, a letter was addressed by one Mr. Sunil Narula, Advocate,  on
behalf of respondent No.1 to three Arbitrators and the  appellant.   It  was
stated in the letter as under:-

“…………..Since M/s  Electrical  Mfg.  Co.  Ltd.  Calcutta,  have  raised  some
disputes in the above-said contract and  instead  of  settling  the   matter
amicably with our client despite  our  client’s   repeated  requests,   have
directly invoked the Arbitration Clause which is  not  in  consonance   with
the terms and conditions of the above referred agreement and therefore,  the
appointment of the arbitrators in  this  matter  is  void  ab  initio.   M/s
Electrical Mfg. Co. Ltd., Calcutta have chosen to neglect their own  written
submissions to our  client in which they had agreed to discuss   and  settle
the  matter amicably with our client  in  accordance  with   the  terms  and
conditions of the agreement and  this was also  a   condition  precedent  to
the invocation of Arbitration Clause 26.1 of the said agreement.


Our clients M/s Power Grid Corporation of  India  Ltd.  are  initiating  the
appropriate legal  proceedings  in  the  Hon’ble  High  Court  of  Delhi  to
challenge the appointment of Shri J.C.Jain, Shri P.P. Agarwal and  Shri  Som
Gupta, the addressee No. 1,2 and 3,  herein  as  Arbitrators  in  the  above
mentioned matter.  As the dispute  in  this  matter  is  to  the  effect  of
legality of the appointment of all the three learned Arbitrators,   you  are
requested to abstain from  and/or postpone the arbitration  proceedings  for
a period of 60 days, which shall be just, reasonable and in the interest  of
justice and  during  this  period  our  client  shall  be   able  to  obtain
necessary orders from the Hon’ble High Court of Delhi.”


On 20.4.1993, fourth meeting of the Arbitral  Tribunal  was  held  at  10.30
a.m. as scheduled.  The relevant minutes of the meeting were as under:-


“It was noted that the minutes of the third meeting held on 7th April,  1993
were sent to M/s NTPC and M/S PGCIL and  have  been  acknowledged  by  them.
Acknowledgement copy taken into record.


It was, however, noted that regret that no representative of M/s  NTPC,  M/s
PGCIL turned up for the hearing.


No compliance was made by the aforesaid respondents to the directives  given
to them in the second and third meetings dated  11.02.1993  and  7th  April,
1993, respectively.


Despite repeated directives from the Arbitrators respondents did not  appear
for the hearing of 20.04.1993 at 10.30 a.m..  In pursuance of  the  decision
taken by the Arbitrators at the  hearing  dated  7.04.1993  the  Arbitrators
proceeded with the hearing ex-parte.


The Arbitrators received on 17.04.1993 at Lucknow a letter dated 9th  April,
1993 from one Mr.  Sunil  Narula,  Advocate  claiming  to  be  acting  under
instructions from PGCIL.   The  contents  of  the  letter  were  considered.
Arguments of EMC’s representative Mr. M.K. Kureshi  were  also  heard.   The
Arbitrators decided to proceed with the hearing.


At 11.10 a.m. Mr. Sunil Narula accompanied by an officer of  PCGIL  came  to
the hearing.  Since Mr. Narula did not have a proper letter of authority  to
appear before the Arbitrators on behalf of PGCIL in respect of  the  dispute
under arbitration, and since the directives given by the Arbitrators in  the
previous meetings had not been complied with by PGCIL, the Arbitrators  were
unable to entertain any submission of Mr.  Narula.   The  hearing  proceeded
further thereafter.


M/s EMC submitted through  their  letter  No.  EMC/009/ARB  dated  20.4.1993
additional documents (12 nos.) as per list attached with the letter.   These
were taken on record.


The following issues were framed:


Whether EMC is entitled to the various claims mentioned in  para  6,  Clause
(i) to (xvi) and para 7, 8, 9 and 17(d) of the Statement of Claim?   If  so,
to what effect and extent.

Whether EMC is entitled to claim interest  mentioned  at  the  end  of  Para
17(d)?  If so, to what effect and extent.

Whether EMC is entitled to say other relief in  the  present  circumstances?
If so, to what effect and extent.

Mr. M.K. Kureshi proceeded to get various documents produced  by him  before
Arbitrators, proved by Mr. Kalyan Kumar Ghosh, Manager (Project  Monitoring)
EMC Ltd., Exhibit I to XXV as per details enclosed  with  minutes  were  got
proved.

      The hearing will continue on Wednesday the 21st  April,  1993  at  the
same place and venue i.e. 89, Sundar Nagar, New Delhi at 10.30 a.m.”

17.   The aforesaid minutes noted the appearance of   Mr.  Sunil  Narula  at
about 11.10 a.m. and that since he did  not   have  appropriate   authority,
and the directives  given in the  previous meeting  were not complied  with,
 no submissions  were entertained  by  the  Arbitrators.   Said  Mr.  Narula
within  an  hour  thereafter  sent  an  Express  Telegram  to  the  Convener
Arbitrator as under:-

                              “EXPRESS TELEGRAM

Sh. Som Gupta
Convenor Arbitrator                     Sh Som Gupta
89, Sunder Nagar (Ist Floor)            C-8/3, Park Road
New Delhi                               Lucknow-226 001

Ref.: Arbitration proceedings regarding contract 01/CC/75-77
for 400KV Kanpur-Etah & Kanpur-Kanpur Line.

I appeared on 20.4.93 on behalf of POWERGRID before the learned  arbitrators
at 89, Sunder Nagar, New Delhi and submitted a Vakalatnama duly  authorizing
me to represent (POWERGRID CORPORATION before the learned Arbitrators.   The
learned arbitrators refused to  accept  the  Vakalatnama  and  made  a  pre-
condition to the effect that POWERGRID should  first  make  the  payment  of
expenses of the Arbitration Proceedings and also submit a  proper  authority
letter granting extension of time for making the award by another  4  months
in order to allow the POWERGRID to  present  the  case  before  the  Learned
Arbitrators.

In the above circumstances, the arbitration proceedings being  held  by  the
Learned Arbitrators in the above matter is illegal,  arbitrary  and  against
the principles of natural justice.

(SUNIL NARULA)
ADVOCATE, DELHI
20.4.1993”

18.   Nobody appeared on behalf  of  respondent  No.1  before  the  Arbitral
Tribunal on 21st, 22nd  and  23rd  April,  1993.   The  matter  having  been
concluded  by  23.04.1993,  the  Arbitral  Tribunal  by  its   award   dated
05.05.1993 found that the appellant had proved its case and was entitled  to
a sum of    Rs. 72,69,096/-  as against its claim of  Rs.3.98  crores.   The
award was then forwarded to the Court to be made Rule of the Court in  terms
of the provisions of the Arbitration Act, 1940 (hereinafter referred  to  as
the “Act”).  Copy of the award and notice of filing of the  award  in  Court
were given to all the parties.  The application for making  the  award  Rule
of the Court was registered as  CS(OS)  No.1201  of   1993  and   objections
under Section 30 and 33 of the Act filed by respondent  No.1  were  numbered
as  IA No.8638 of 1993.

19.   By his judgment and order dated 10.02.2006,   the   Single  Judge   of
the High Court dismissed the objections preferred  by  respondent  No.1  and
made award dated 5.05.1993 awarding a sum of Rs. 72,69,096/-  in  favour  of
appellant, Rule of the Court against  respondent No.1.   The  appellant  was
also held entitled to simple interest @ 12 % per annum from the date of  the
award till the date of the   decree and to simple interest @  9%  per  annum
from the date of the decree till its realization.   The appellant  was  also
held entitled to  costs  from  respondent  No.1  which  were  quantified  at
Rs.7,500/-.  During the course of his judgment,  the  learned  Single  Judge
observed as under:-

“29.It is not in dispute that  notices  were  duly  served  upon  respondent
No.1.  It is also not in dispute that respondent No.2 had knowledge  of  the
proceedings as the relevant  documents  had  been  forwarded  to  respondent
No.2.  Despite this fact respondent No.2 failed to enter appearance.   I  am
also unable to accept the  plea  of  the  learned  senior  counsel  for  the
respondent  No.1  that  there  was  no  power  in  the  Arbitrators  to  add
respondent No.2 as a party.  In fact no  such  addition  was  necessary  and
what ought to have been done was  only  to  substitute  respondent  No.2  in
place of respondent No.1.

30.    The  respondent  No.2  even  appeared  subsequently  but  instead  of
participating in  the  matter  was  only  interested  in  adjournment.   The
Arbitrators, even assuming the arguments of  the  counsel  appearing  before
the Arbitrator to be correct, wanted an  extension  of  time  failing  which
they wanted to proceed with the Arbitration so that the award could be  made
within the statutory period of time.  Respondent No.2  was  not  willing  to
join in the extension of time.  In such a situation  respondent  No.2  ought
to have taken immediate legal remedy to at least challenge the  constitution
of the Tribunal if so advised.  This respondent No.2 did  not  do  but  just
kept silent over the matter.   The  allegations  and  submissions  that  the
statement of claim was not  available  with  respondent  No.2  or  that  the
record is silent about the same or as to what transpired  on  20.4.1993  are
clearly afterthoughts.  It is also to be kept  in  mind  that  there  was  a
panel of Arbitrators.  Two Arbitrators  were  appointed  by  an  independent
agency.  There could have been hardly any grievance made by respondent  No.2
about the composition of the Tribunal.

31.   Respondent No.2 itself had addressed a communication  dated  24.8.1992
to the  Institute  of  Engineers  and  have  made  admission  themselves  in
paragraph 2.26 (iii) of the objections that they had received intimation  of
the appointment of Arbitrators on 12.11.1992.   The  proceedings  have  also
been sent to  respondent  No.  2.  Respondent  No.  2  having  not  appeared
negligently  or  willfully,  a  further  opportunity  was   given   by   the
Arbitrators to the said  respondent  on  7.4.1993……….……………..      Respondent
No. 2 apparently was not willing to join  the  Arbitration  proceedings  and
negligently kept away  and  did  not  even  take  steps  to  challenge  such
Arbitration proceedings.  There cannot be  an  indefinite  period  for  pre-
Arbitration  settlement  proceedings  to  continue.   The   Contract   stood
concluded in 1988  and  despite  all  discussions  no  settlement  could  be
finalized right till 1991.  The dispute resolution  mechanism  was  followed
in view of the letter of the petitioner dated 18.7.1991 with a  copy  marked
to the Engineer of the project and the  petitioner  clarified  in  terms  of
letter dated 2.09.1991 that the disputes raised by its  earlier  letter  had
been raised before the Engineer or the Contract in terms of Clause  26.4  of
the terms and conditions of Contract.  The Engineer did not  answer  to  the
claim within thirty(30) days of  the receipt of the notice as  was  required
to be done and it is  in  view  thereof  that  the  Arbitration  Clause  was
invoked on 20.3.1992.”

20.   The matter was carried further by  respondent No.1  by  filng  FAO(OS)
No.196 of 2006 which appeal came to be allowed  by the   Division  Bench  of
the High Court vide its judgment and order dated 4.07.2008.    The  Division
Bench found that the Arbitral Tribunal had acted in utter haste  in  rushing
through the arbitration proceedings without affording  proper  and  adequate
opportunity to respondent No.1 in presenting its case.  The  Division  Bench
felt that the interest of justice would be best served if   the  matter  was
referred again to a Sole  Arbitrator to adjudicate the dispute  between  the
parties afresh after giving due opportunity to both the parties.    Allowing
the appeal and setting aside the order passed by the  learned  Single  Judge
and the award made by the Arbitrator, the matter was referred  to  the  Sole
Arbitrator. During the course of its judgment, the  Division  Bench  of  the
High Court observed, inter alia:-

      “……..We are of the view that the Arbitrators have unnecessarily  acted
in haste in concluding the arbitral  proceedings.  Once  the  appellant  had
appeared before them, the least they should have done  was  to  afford  some
reasonable time to the appellant to file its objections to the statement  of
claim filed by the respondent EMC. The Arbitrators also could have  given  a
pre-emptory notice to the  appellant  before  proceeding  ex  parte  against
them. Even after proceeding ex-parte against the appellant  the  Arbitrators
still could have called upon them to cause appearance in the matter……………….”
      “… The appellant had appeared on 9th April, 1993 as well  as  on  20th
April, 1993, but they were not allowed to participate in the  proceedings[1]
and thereafter within four days i.e. from 21.4.1993 to 25.04.1993  the  same
were concluded. ……..”
      “……….Although, the conduct of  both  the  corporations  i.e.,  NTPC  &
NPTC, (appellant) in adopting a very casual and lackadaisical  approach,  in
not timely taking the actions including for an appointment of an  arbitrator
and also for their non-appearance  before  the  Arbitral  Tribunal  exhibits
their total insensitivity to the  monetary  claims  of  the  duly  appointed
contractor and their own financial interests yet at the same time  the  said
contractor i.e., EMC cannot completely absolve itself to share the blame  by
not adhering to the said communication dated 28.11.1992. The respondent  EMC
was not oblivious  of  the  said  fact  of  transfer  of  ownership  of  the
transmission system by NPTC in favour of the appellant (NPTC), although  the
same came to be notified through an ordinance on 8.1.1993.”

21.   While issuing notice in the  petition  for  special  leave  to  appeal
preferred by the appellant, this Court by its order dated 01.08.2008  stayed
the operation of the judgment  and  order  passed  by  the  Division  Bench.
Consequently, the matter did not proceed before the  Sole  Arbitrator  named
in the judgment of the Division Bench.  The  parties  having  exchanged  the
pleadings, we heard  Mr.  C.Mukund,  learned  Advocate  in  support  of  the
appellant and Mr. Parag Tripathi, learned  Senior  Advocate  for  respondent
No.1.

22.      Having heard the learned Counsel and gone through  the  record,  in
our view, the instant matter raises questions ; a) Whether  arbitration  was
validly  invoked  in  the  matter;  b)  Whether  the  appointment   of   the
Arbitrators was in terms  of  the  relevant  Clauses  of  the  Contract;  c)
Whether respondent No.1 was  aware  of  such  invocation  and  consequential
proceedings; and d) Whether the Arbitral Tribunal was right in  refusing  to
adjourn the proceedings and proceed with the matter.  Our answers  to  these
questions are as under:-

 a)     In terms of the provisions of Clause 26 (1)  of  the  Contract,  the
appellant vide letters dated 18.7.1991  and  02.09.1991  had  requested  the
“Engineer” to look into the disputes as  raised  by  the  appellant.   These
letters were admittedly received by NTPC.  As stipulated in  Clause  26  (1)
read with Clause 26 (4), in the event of the “Engineer”  failing  to  notify
his decision within 30 days  after  being  requested,  the  concerned  party
would be within its rights  to  require  that  the  matters  in  dispute  be
referred to arbitration.   Since  nothing  was  done  with  respect  to  the
request  made  by  the  appellant  within  30  days  of   the   receipt   of
communication dated  18.07.1991  or  even  the  one  dated  02.09.1991,  the
appellant could validly require that the matters in dispute be  referred  to
arbitration.  Even assuming that in terms of  letter  dated  28.11.1991,  it
was  NPTC  who  was  to  be  concerned  with  the  matters  in  dispute,  no
appropriate decision was taken even within 30 days  of  this  communication.
In the circumstances, invocation of arbitration by the  appellant  vide  its
letter dated 20.03.1992 was perfectly valid and in terms of the Contract.

b)    A copy of aforesaid letter dated  20.03.1992  addressed  to  NTPC  was
admittedly forwarded  to  and  received  by  NPTC.   Neither  of  them  took
appropriate and required steps in the matter within 60 days as  contemplated
by Clause 26.6.1 of the Contract.  In the circumstances, the step  taken  by
the appellant to approach Institution of Engineers  (India)  requesting  its
President to appoint the arbitrator  in  terms  of  said  Clause,  vide  its
letter dated 07.07.1992 was also in keeping with the express  terms  of  the
Contract.  It is crucial to note that a telegram was sent on  24.08.1992  on
behalf of NPTC requesting the President, Institution  of  Engineers  (India)
to keep the action regarding appointment of arbitrator on  their  behalf  in
abeyance.  It was stated that a detailed  letter  was  to  follow.   However
nothing was done in the matter for  more  than  a  month  and  the  detailed
letter was never sent. In the circumstances, the President,  Institution  of
Engineers  (India)  was  absolutely  right  and  justified  in  making   the
appointment of the Second Arbitrator on 29.09.1992.  The appointment of  the
Third Arbitrator was in any case within the powers of the President.   Thus,
appointment of the Second and  Third  Arbitrator  and  constitution  of  the
Tribunal cannot be found fault with.

c)    The record is clear that NTPC was aware of  the  communications  dated
18.07.1991 and 02.09.1991.  If under the directions  of  the  Government  of
India, NPTC was to take  over  matters  including  those  related  with  the
Contract in question, NPTC ought to have been appraised  of  the  issues  in
question by NTPC.  In any case, the  telegram  dated  24.08.1992  as  stated
above, expressly shows complete  awareness  on  part  of  NPTC  and  yet  no
further steps were taken by NPTC.  No  detailed  letter  as  stated  in  the
telegram was ever sent. Further, respondent No.1 which is the  successor-in-
interest was made aware of the pendency of proceedings before  the  Arbitral
Tribunal but chose not to  appear  and  take  part.  Minutes  of  first  two
meetings of  the  Arbitral  Tribunal  were  forwarded  to  and  received  by
respondent     No.1.  Even telegrams seeking  and  granting  adjournment  of
the proceedings were sent to respondent No.1.  When  in  the  meeting  dated
07.04.1993 the Schedule for days beginning from  20.04.1993  was  fixed  and
copy of the minutes was sent  to  respondent  No.1,  the  Advocate  for  the
respondent No.1 addressed a letter to the Arbitration  on  09.04.1993.  This
letter  not  only  indicates  complete  awareness  of  the  proceedings  but
displays  definite  idea  having  crystallized   to   initiate   appropriate
proceedings in the High Court. If that be  so,  nothing  stopped  respondent
No.1 from initiating such challenge, which never happened.  The  least  that
it could do in the circumstances was to  be  ready  to  participate  in  the
proceedings  and  be  ready  on  merits  of  the  matter.  However  even  on
20.04.1993, i.e. eleven days after the letter was sent, it was  not  willing
to participate. If it wanted adjournment in the matter,  it  ought  to  have
consented to the extension of time as  the  Arbitral  Tribunal  had  rightly
indicated.  The conduct of respondent  No.1  as  rightly  commented  by  the
Division Bench of the High Court, was extremely casual.

d)   The Arbitral Tribunal in the present case had  entered  upon  reference
and held its first meeting on 13.01.1993. The mandate of Section  28(1)  and
(2) of the Act read with Schedule I, Clause  3  of  the  Act  was  that  the
statutory period to complete the proceedings and make  the  award  was  four
months after entering on the reference. The minutes  of  the  meeting  dated
07.04.1993 show awareness that the period would expire  on  12.05.1993.  The
law on the point is clear that in such  circumstances,  the  enlargement  of
time could be possible if parties to the arbitration  agreement  consent  to
such enlargement. The decision of this  Court  in  Hari  Krishna  Wattal  v.
Vaikunth Nath Pandya by L.RS. &  Ors.[2]  is  quite  eloquent  and  relevant
paragraphs thereof are:-

“6. Section 3 of the Arbitration Act, 1940 provides:

“An  arbitration  agreement,  unless  a  different  intention  is  expressed
therein, shall be deemed to include the provisions  set  out  in  the  First
Schedule insofar as they are applicable to the reference.”

7. The First Schedule has 8 clauses describing the implied conditions of  an
arbitration agreement. Clause 3 reads as follows:

“The arbitrators shall make their award within four  months  after  entering
on the reference or after having been  called  upon  to  act  by  notice  in
writing from any party to the arbitration agreement or within such  extended
time as the Court may allow.”

10.   The question depends upon the true construction of Section  28.  There
is no doubt that the Arbitrator is expected to make his  award  within  four
months of his entering on the reference or on his being called upon  to  act
or within such extended time as the Court may allow.  Reading  Clause  3  of
the Schedule along with Section 28 one finds that the power to  enlarge  the
time is vested in the Court and not in the Arbitrator. Clause 3 and  Section
28(1) exclude by necessary  implication  the  power  of  the  Arbitrator  to
enlarge the time. This is emphasised by Section 28(2)  which  provides  that
even when such a provision giving the Arbitrator power to enlarge  the  time
is contained in the agreement, that  provision  shall  be  void  and  of  no
effect. The head-note of Section 28 brings out the force  of  this  position
in law by providing that the power is of the Court only to enlarge time  for
making the award.

11. Sub-section (2) of Section 28, however, indicates one exception  to  the
above rule that the Arbitrator cannot enlarge the time,  and  that  is  when
the parties agree to such an enlargement. The occasion  for  the  Arbitrator
to enlarge the time occurs only after he is called upon to proceed with  the
arbitration or he enters upon the reference. Hence, it is clear that if  the
parties agree to the enlargement of time after the  Arbitrator  has  entered
on the reference, the Arbitrator has the power to enlarge it  in  accordance
with the mutual agreement or consent of the parties.  That  such  a  consent
must be a post reference consent, is also clear  from  Section  28(2)  which
renders null and void a provision in the original agreement to that  effect.
In a sense where a provision is made in  the  original  agreement  that  the
Arbitrator may enlarge the time, such  a  provision  always  implies  mutual
consent for enlargement but such mutual consent initially expressed  in  the
original agreement does not save the  provision  from  being  void.  It  is,
therefore, clear that the Arbitrator gets the jurisdiction  to  enlarge  the
time for making the award only  in  a  case  where  after  entering  on  the
Arbitration the  parties  to  the  arbitration  agreement  consent  to  such
enlargement of time.”

In the circumstances, if the Arbitral  Tribunal  insisted  upon  appropriate
consent to extend the time, no fault could be found with. At the same  time,
if respondent No.1 was not  willing  to  give  such  consent,  the  Arbitral
Tribunal had to go on  with  the  matter  and  make  the  award  within  the
statutory period. The Division Bench was not right  in  observing  that  the
Arbitral Tribunal showed undue haste in the matter.

23.   In our view, the  Division  Bench  was  not  right  and  justified  in
allowing the appeal and setting aside the judgment and order passed  by  the
Single Judge.  We, therefore, allow this appeal, set aside the judgment  and
order passed by the Division Bench of the High Court of  Delhi  and  restore
the judgment and order dated 10.02.2006 passed by the Single  Judge  of  the
High Court of Delhi.

24.  This appeal is allowed with no order as to costs.




                                                        ….....………………………………J.
                                      (Fakkir Mohamed Ibrahim Kalifulla,)

                                                         ....…………………………………J.
                                                      (Uday Umesh Lalit)

New Delhi,

July 20, 2016


-----------------------

[1]


      [2] This observation is not correct. On 9.4.1993 a letter was
addressed by the Advocate. No hearing was fixed on 9.4.1993.

[3]

      [4] 1973 (2) SCC 510

For the Latest Updates Join Now