Supreme Court of India (Division Bench (DB)- Two Judge)

Appeal (Civil), 3702 of 2015, Judgment Date: Apr 16, 2015

 

In the light of our above conclusion, we hold that the learned Judge  having
failed to appreciate the legal position  as  regards  the  existence  of  an
arbitration agreement in the MoU irrespective of the failure of the  parties
to reach a full-fledged agreement with respect  to  the  various  terms  and
conditions contained in the MoU for a joint  venture,  the  said  conclusion
and judgment of the  learned  Judge  is  liable  to  be  set  aside  and  is
accordingly  set   aside.   Since   the   respondent   has   expressed   its
disinclination to agree to express its concurrence and thereby  the  parties
failed to appoint an Arbitrator under the agreed procedure, it is  necessary
for this Court to appoint an Arbitrator. Therefore, while setting aside  the
judgment impugned in this appeal, we  hereby  appoint  Hon'ble  Ms.  Justice
Rekha Manharlal Doshit, resident of C-5,  402,  Deo  Sangam  Flat,  Guartgam
Road, Near Gandhi Nagar, Gujarat, former Chief Justice of Patna  High  Court
and former Judge of Gujarat High Court as the sole Arbitrator to  adjudicate
the disputes that  have  arisen  between  the  parties  on  such  terms  and
conditions as the sole Arbitrator deems fit  and  proper.  Undoubtedly,  the
learned sole Arbitrator shall decide all the disputes  arising  between  the
parties under the MoU, without being influenced by any prima  facie  opinion
expressed in this  order  with  regard  to  the  respective  claims  of  the
parties.

                                                                  Reportable

                        IN THE SUPREME COURT OF INDIA
                        CIVIL APPELLATE JURISDICTION

                       CIVIL APPEAL NO.  3702 OF 2015
                         (@ SLP (C) NO.1963 of 2014)

Ashapura Mine-Chem Ltd.                                       ....Appellant


                                   VERSUS


Gujarat Mineral Development Corporation                      ....Respondent


                               J U D G M E N T


Fakkir Mohamed Ibrahim Kalifulla, J.

Leave granted.

This  appeal  is  directed  against  the  judgment  of  the  High  Court  of
Judicature of Gujarat at Ahmedabad in Arbitration Petition No. 9/2013  dated
27.9.13/04.10.2013. By the impugned judgment, the learned  Single  Judge  of
the High Court dismissed the appellant's application filed under Section  11
of the Arbitration and  Conciliation  Act,  1996  (hereinafter  referred  to
"Act").

Short facts which are required to be noted are that the  appellant  and  the
respondent entered into a Memorandum of Understanding (MoU)  on  17.08.2007.
Under the said MoU, the appellant proposed to  constitute  a  joint  venture
along with Chinese Company, namely, "M/s Qing TongXia  Aluminium  Group  Co.
Ltd. Ningxia of China (hereinafter referred to as  "QTX")  as  well  as  the
respondent for setting up an alumina plant of appropriate  capacity  in  the
Kutch District of Gujarat. The MoU  also  records  that  the  Government  of
Gujarat agreed to encourage and  support  the  proposed  joint  venture  for
setting up of  the  alumina  plant.  The  respondent  agreed  to  supply  on
priority basis, medium grade Bauxite to  the  proposed  plant  from  its  10
existing and 18 expected Bauxite mining leases in the Kutch District.

The other relevant terms were that the  appellant  should  arrange  for  the
equity participation of the QTX in the  proposed  joint  venture,  that  the
respondent should invest in the equity of the joint venture  to  the  extent
determined by the Government of Gujarat but  not  exceeding  26%  while  the
appellant and the QTX should hold 74% of the equity.  The  capacity  of  the
proposed plant should  be  1.00  million  tonnes  per  annum  which  may  be
enhanced subsequently. On the part of the respondent, it should  assist  the
joint venture in obtaining the  required  land  for  locating  the  project.
Under Clauses 5, 6, 8, 10 and 11, the quantity of the medium  grade  Bauxite
to  be  supplied  by  the  respondent,  the  grade  of  the   Bauxite,   the
specifications, the rate at which it was to be  supplied,  the  time  within
which such supply should be effected were all set out which also included  a
long term agreement for the supply to be entered into.

MoU also stipulated certain other conditions  by  which  the  appellant  was
obligated upon to reimburse  to  the  respondent,  within  60  days  of  the
signing of the MoU, an amount of Rs.3.94 crores being  the  direct  expenses
incurred by the respondent on its Alumina Project and related matter. It  is
not in dispute that within the stipulated time limit the appellant gave  its
cheque for the said sum but the respondent did not encash the same. It  also
provided for the appellant to pay the respondent a further  sum  of  Rs.6.25
crores within 60 days of the execution of the MoU by way of signature  bonus
apart from providing a bank guarantee to the value of Rs.10 crores  for  the
due observance for the joint venture by  the  appellant  under  the  various
terms and conditions of the MoU within 30 days of the signing of the MoU.

Clause 12 of the MoU specifically provided that the  rights  and  privileges
were not transferable for a period of five years and  the  appellant  should
not exit the project/joint venture for a period  of  five  years  after  the
commencement of commercial production.

Under Clause 19, it was stipulated that the MoU was subject to  approval  of
the Board of Directors of the appellant as well as the respondent, that  the
equity investment and decisions of the respondent should be subject  to  the
concurrence of the Government  of  Gujarat,  while  the  investment  of  the
appellant should  be  subject  to  approval  of  its  shareholders.  It  was
specifically mentioned that both the appellant  and  the  respondent  should
endeavour to obtain necessary approval within three months from the date  of
execution of the MoU. It was further specifically mentioned that on  getting
necessary approval by both  sides,  the  MoU  would  be  converted  into  an
agreement between the appellant and  the  respondent.  Clause  21  contained
relevant stipulation to the effect that  in  case  the  concurrence  of  the
Government of Gujarat was not forthcoming for equity  participation  in  the
project within six months of the signing  of  the  MoU,  the  MoU  would  be
construed as one relating to long term supply of  medium  grade  Bauxite  to
the joint venture by the respondent from its Kutch mines.

The more important Clauses contained in MoU pertaining  to  arbitration  are
found in Clauses 26 and 27 which read as under:

"26. In the event of difference disputes  arising  between  the  parties  in
respect of any matter  arising  out  of  and  relating  to  this  MoU,  such
dispute/difference shall, in the first instance,  be  resolved  amicably  by
mutual consultation within 45 days of the reference of  disputes  by  either
party.

27. If amicable settlement is not reached  between  the  parties  then  such
unresolved dispute or difference of opinion concerning or arising  from  the
MoU and its implementation, breach or termination whatsoever, including  any
difference or dispute as to the interpretation of any of the  terms  of  the
MoU, shall be referred to the arbitration or a sole arbitrator appointed  to
GMDC and AML.  The Arbitrator shall give reasoned  award.   The  Arbitration
shall be governed by Arbitration and  Conciliation  Act,  1996  (India)  and
conducted in the city of Ahmedabad.  The language of  Arbitration  shall  be
English.   The  parties  shall  share  the  cost  of   Arbitration   equally
Arbitration clause to be acceptable to the Financing sources."



Subsequent to the signing of the above MoU, there was a Board Resolution  of
respondent dated 29.10.2007. The  said  Resolution  stated  that  the  Board
resolved to accord its approval to the MoU executed  on  17.08.2007  between
the appellant and the respondent subject to the modifications noted  in  the
said resolution. Subsequent to the said resolution  which  was  communicated
to the appellant, correspondence was exchanged  between  the  appellant  and
the respondent and on some occasions with the  Principal  Secretary  of  the
State of Gujarat between  17.12.2007  and  10.03.2010.  There  was  a  Board
Resolution of the respondent dated 18.03.2010 which disclose that the  Board
decided to the effect that in the light of the new mineral policy  announced
by the State Government in  November,  2009,  major  changes  were  made  in
respect of Bauxite also and, therefore, it was not inclined  to  extend  the
validity of the proposed MoU  and  also  decided  to  invite  fresh  EOI  in
Bauxite for higher value addition  in  alumina.  However,  in  a  subsequent
communication dated 26.07.2010, the respondent informed the  appellant  that
to maintain parity necessary modification in the  terms  and  conditions  of
the MoU dated 17.8.2007 as approved by the  Board  of  the  respondent  were
communicated to the State Government for  approval  which  was  awaited  and
that on receipt of such approval, a fresh MoU may have to be executed.

But subsequently, by communication dated 25.04.2011, the respondent  tacitly
informed the appellant that it decided to forthwith  cancel  the  MoU  dated
17.08.2007 in view of failure on the part  of  the  appellant  in  complying
with various terms and conditions of the MoU.  The respondent,  thus,  threw
the blame on the appellant for the proposed project not  being  able  to  be
finalized.

In response to the said letter  dated  25.04.2011,  the  appellant  wrote  a
detailed reply on 11.07.2011 wherein the appellant expressed its  desire  to
amicably resolve the  dispute  and  requested  the  respondent  to  make  an
attempt for an  amicable  settlement  as  regards  the  issues  and  alleged
breaches  mentioned   in   the   respondent's   letter   dated   25.04.2011.
Subsequently, the appellant caused a legal notice dated  07.12.2012  to  the
respondent, wherein it was claimed that its attempt to amicably resolve  the
dispute as provided under Clause 26 of the MoU  failed  and,  therefore,  it
decided to invoke Clause  27  of  the  MoU  to  appoint  an  Arbitrator  and
suggested the name of a retired High Court Judge for  appointment  with  the
concurrence of the respondent or else the  appellant's  decision  to  invoke
Section 11 of the Act.

On behalf of the respondent, a reply  was  addressed  to  the  appellant  on
04.01.2013 stating that there was no  fault  whatsoever  on  its  side  and,
therefore, there was no question of any obligation to be  fulfilled  on  its
side and it also expressed its decision not to concur  for  the  appointment
of the Arbitrator.

It was in the above stated sequence of events i.e. from the date of  MoU  to
the date of filing of the application, the  appellant  approached  the  High
Court by filing an application under Section 11 of the Act  and  sought  for
appointment of an Arbitrator.  By the impugned order, the High Court  having
rejected the appellant's application, the appellant has  come  forward  with
this appeal.

We heard Mr. Dushyant Dave, learned senior counsel  for  the  appellant  and
Mr. Vikas Singh, learned senior counsel for the  respondent.   Mr.  Dushyant
Dave after referring to the above course of  events  that  has  taken  place
between the appellant  and  the  respondent  from  the  date  of  MoU  dated
17.8.2007 till the rejection of the  Arbitration  Application  by  the  High
Court, contended that since indisputably the respondent terminated the  MoU,
the conclusion of the High Court that the same was a still-born  was  wholly
unjustified.  The learned senior counsel submitted that even if the MoU  for
the proposed joint venture did not ultimately fructify into the creation  of
the joint venture, Clauses 26 and 27 of the MoU by virtue  of  the  specific
terms  contained  therein  would  operate  as  stand-alone   agreement   for
arbitration and with reference to the said agreed terms,  since there was  a
 consensus ad idem between  the  parties,  the  High  Court  ought  to  have
appointed the Arbitrator exercising its power under Section 11 of  the  Act,
inasmuch as the respondent declined to express its  consent  for  the  named
Arbitrator suggested by the appellant.

As against the above submission Mr.  Vikas  Singh,  learned  senior  counsel
appearing for the respondent vehemently submitted that the  High  Court  was
able to highlight that the parties  had  no  consensus  ad  idem  even  with
reference to the very MoU itself and in  the  circumstances,  there  was  no
scope for applying Clauses 26 and 27 for the appointment  of  Arbitrator  as
claimed by the appellant.

While Mr. Dushyant Dave, learned senior counsel  placed  reliance  upon  the
decisions in Enercon (India) Limited & Ors. v. Enercon GMBH &  Anr.  -  2014
(5) SCC 1, Reva Electric Car Company Private Ltd. v. Green Mobil - 2012  (2)
SCC 93 and Today Homes and Infrastructure Pvt. Ltd. v. Ludhiana  Improvement
Trust and Anr. - 2014 (5) SCC 68, Mr. Vikas Singh relied upon the  decisions
reported as SBP & Co. v. Patel Engineering Ltd. & Anr. - 2005 (8)  SCC  618,
National Insurance Company Ltd. v. Boghara Polyfab Pvt. Ltd. - 2009 (1)  SCC
267 and Chloro Controls India Pvt. Ltd. v. Severn Trent  Water  Purification
Inc. & Ors. - 2013 (1) SCC 641 in support of his submissions.

Having heard the submissions of the respective counsel,  we  find  that  the
sum and substance of the submission  of  Mr.  Dushyant  Dave  was  that  the
arbitration Clause contained in Clause 27 of  the  MoU  was  an  independent
arbitration agreement and, therefore, even if respondent chose to  terminate
the MoU dated 17.8.2007, the Arbitration agreement would continue to  remain
and consequently the parties are entitled to invoke the said Clause  27  and
exercise their  option  for  appointment  of  an  Arbitrator  and  seek  for
concurrence of the other party. The learned senior  counsel  contended  that
since the respondent expressed  its  decision  to  terminate  the  MoU,  the
appellant after  exhausting  its  attempt  for  an  amicable  settlement  at
bilateral level as between the appellant  and  the  respondent  by  invoking
Clause 26 had no other option but to  invoke  Clause  27  and  opt  for  the
appointment of a  retired  Judge  Hon'ble  Mr.  Justice  B.N.  Mehta  as  an
Arbitrator and sought for the concurrence of the  respondent.   The  learned
senior counsel submitted that when the respondent  refused  to  concur  with
the appointment of the said learned Judge as an  Arbitrator,  the  appellant
was well justified in approaching the High Court under Section  11  for  the
appointment of  an  Arbitrator.   The  learned  senior  counsel,  therefore,
contended that the rejection of the said application filed under Section  11
of the Act by  the  impugned  order  is  liable  to  be  set  aside  and  an
Arbitrator has to be appointed.

According to Mr. Vikas Singh, learned  senior  counsel  for  the  respondent
inasmuch as the MoU itself was not a concluded contract, Clauses 26  and  27
of the said MoU do not survive and  consequently  there  was  no  scope  for
appointment of an Arbitrator by invoking Clause 27 of the MoU.

To appreciate the respective contentions and having regard  to  the  law  on
this issue been already settled in more than one decision,  we  are  of  the
view  that  the  statement  of  law  so  declared  by  this  Court  can   be
straightaway noted in order to render our decision in  tune  with  the  said
proposition of law declared by this Court.

In this context, we find, the reliance placed upon  by  Mr.  Dushyant  Dave,
learned  senior  counsel  for  the  appellant  on  the  decisions  in   Reva
Electrical Car Company Private Ltd. (supra), Today Homes and  Infrastructure
Pvt. Ltd. (supra) and Enercon (India)  Limited  (supra)  fully  support  the
stand of the  appellant.   The  decision  in  Reva  Electrical  Car  Company
Private Ltd. (supra) was a case which arose under Section 11 of the Act.   A
question was raised on behalf of the respondent in  the  said  case  to  the
effect that with the termination of the MoU itself, the  Arbitration  Clause
would cease to exist.  Dealing with the said  question,  the  learned  Judge
has held as under in paragraphs 54 and 55:
 "54. Under Section  16(1),  the  legislature  makes  it  clear  that  while
considering any objection with respect to the existence or validity  of  the
arbitration agreement, the arbitration  clause  which  formed  part  of  the
contract, has to be treated as an agreement independent of the  other  terms
of the contract. To  ensure  that  there  is  no  misunderstanding,  Section
16(1)(b) further provides that even if the Arbitral Tribunal concludes  that
the contract is null and void, it should not result, as a matter of law,  in
an automatic  invalidation  of  the  arbitration  clause.  Section  16(1)(a)
presumes the existence of a valid arbitration clause and mandates  the  same
to be treated as  an  agreement  independent  of  the  other  terms  of  the
contract. By virtue of Section 16(1)(b),  it  continues  to  be  enforceable
notwithstanding a declaration of the contract being null and void.  In  view
of the  provisions  contained  in  Section  16(1)  of  the  Arbitration  and
Conciliation Act, 1996, it would not be possible to  accept  the  submission
of Ms Ahmadi that with  the  termination  of  the  MoU  on  31-12-2007,  the
arbitration clause would also cease to exist.

55. As noticed earlier, the disputes that have arisen  between  the  parties
clearly relate  to  the  subject-matter  of  the  relationship  between  the
parties which came into existence through the MoU. Clearly,  therefore,  the
disputes raised by the petitioner need to be referred to arbitration.  Under
the arbitration clause, a reference was to be made that  the  disputes  were
to be referred to a single arbitrator. Since  the  parties  have  failed  to
appoint an arbitrator under the agreed procedure, it is necessary  for  this
Court to appoint the arbitrator."

                                                            (Emphasis added)


In Today Homes and Infrastructure Pvt. Ltd.  (supra),  this  Court  approved
the statement of law stated by the learned  Judge  of  this  Court  in  Reva
Electrical Car Company Private Ltd. (supra). Paragraph 14  can  be  usefully
referred to which reads as under:
"14. The same reasoning was adopted by a member of this Bench (S.S.  Nijjar,
J.), while deciding Reva Electric Car Co. (P) Ltd. v. Green  Mobil,  wherein
the provisions  of  Section  16(1)  in  the  backdrop  of  the  doctrine  of
kompetenz kompetenz were considered and it was inter alia  held  that  under
Section 16(1), the legislature makes it clear  that  while  considering  any
objection with regard to  the  existence  or  validity  of  the  arbitration
agreement, the arbitration clause, which formed part of  the  contract,  had
to be treated as  an  agreement  independent  of  the  other  terms  of  the
contract. Reference was made in the  said  judgment  to  the  provisions  of
Section 16(1)(b) of the 1996 Act, which provides that even if  the  Arbitral
Tribunal concludes that the  contract  is  null  and  void,  it  should  not
result, as a matter of law, in an automatic invalidation of the  arbitration
clause. It was also held that Section 16(1)(a) of the 1996 Act presumes  the
existence of a valid arbitration clause and mandates the same to be  treated
as an agreement independent of the other terms of the  contract.  By  virtue
of Section 16(1)(b) of the 1996 Act, the arbitration clause continues to  be
enforceable, notwithstanding a declaration that the contract  was  null  and
void."
                                                            (Emphasis added)


Again this very question  came  up  for  consideration  in  Enercon  (India)
Limited (supra) to which one of us (F.M.I Kalifulla, J.)  was  a  party.  In
the said decision, the nature of transaction between the  parties  was  more
or less identical to the facts  of  this  case.  The  contention  raised  on
behalf of the appellant in that case was that there can  be  no  arbitration
agreement in the absence of a concluded  contract,  that,  therefore,  there
was no question of an  arbitration  agreement  coming  into  existence  and,
therefore, there was no scope for referring the dispute for arbitration.

As against the  above  submissions,  it  was  contended  on  behalf  of  the
respondent in the said decision that even  if  the  existence  of  the  main
contract is under dispute, the Court is concerned only with the  arbitration
agreement, i.e. the arbitration clause and that when once such a  Clause  is
very much  present,  that  would  by  itself  result  in  the  matter  being
referable for arbitration. In fact, in the said case,  the  Clause  relating
to arbitration was found in Clause No.18.1 which provided for an attempt  to
resolve the dispute, controversy or difference through  mutual  consultation
and if it is not resolved through mutual consultation within 30  days  after
commencement  of  discussion,  then  the  parties  may  refer  the  dispute,
controversy or difference for resolution to an Arbitral Tribunal.

Dealing with the said Clause and the  arguments  raised  on  behalf  of  the
respective parties, the law has been laid down as  under  in  paragraphs  82
and 83 which are to the following effect:
"82. Further, the arbitration agreement contained in Clauses  18.1  to  18.3
of  IPLA  is  very  widely  worded  and  would  include  all  the  disputes,
controversies or differences concerning the legal relationship  between  the
parties. It would include the disputes arising in respect of the  IPLA  with
regard  to  its   validity,   interpretation,   construction,   performance,
enforcement or its  alleged  breach.  Whilst  interpreting  the  arbitration
agreement and/or the arbitration clause, the court must be conscious of  the
overarching policy of least intervention by courts or  judicial  authorities
in matters covered by the Indian Arbitration  Act,  1996.  In  view  of  the
aforesaid, it is not possible for us to accept the submission of Mr  Nariman
that the arbitration  agreement  will  perish  as  the  IPLA  has  not  been
finalised. This is  also  because  the  arbitration  clause  (agreement)  is
independent  of  the  underlying  contract  i.e.  the  IPLA  containing  the
arbitration clause. Section 16 provides  that  the  arbitration  [pic]clause
forming part of a contract shall be treated as an agreement  independent  of
such a contract.

83. The concept of separability of  the  arbitration  clause/agreement  from
the underlying contract is a necessity to ensure that the intention  of  the
parties to resolve the disputes by arbitration does not evaporate into  thin
air with every challenge to the legality, validity, finality  or  breach  of
the underlying contract.  The  Indian  Arbitration  Act,  1996,  as  noticed
above, under Section 16 accepts the concept that the main contract  and  the
arbitration agreement form two independent contracts. Commercial rights  and
obligations are contained  in  the  underlying,  substantive,  or  the  main
contract.  It  is  followed  by  a  second  contract,  which  expresses  the
agreement and the intention of the parties to resolve the disputes  relating
to the underlying contract through  arbitration.  A  remedy  is  elected  by
parties outside the normal civil court remedy. It is true  that  support  of
the national courts would be required to ensure the success of  arbitration,
but this would not detract  from  the  legitimacy  or  independence  of  the
collateral arbitration agreement, even if it is  contained  in  a  contract,
which is claimed to be void  or  voidable  or  unconcluded  by  one  of  the
parties."

                                                            (Emphasis added)


Mr. Vikas Singh, learned senior counsel for the respondent by  referring  to
the Seven Judge Bench decision of  this  Court  in  Patel  Engineering  Ltd.
(supra) sought to contend that the reliance placed upon  the  said  decision
by this Court in Today Homes  and  Infrastructure  Pvt.  Ltd.  (supra)  with
particular reference to the position stated in  paragraph  13  of  the  said
judgment was not appropriate.
We are not inclined to entertain the said submission, as  we  find  that  we
are not concerned with the said  issue  as  to  whether  what  was  held  in
paragraph 13 of Today Homes and Infrastructure Pvt.  Ltd.  (supra)  judgment
was correct or not  when  it  makes  reference  to  the  Seven  Judge  Bench
decision in Patel Engineering Ltd.(supra).  We are only concerned  with  the
question whether an Arbitration Clause contained  in  the  MoU  is  a  stand
alone agreement or not. For that purpose, what  has  been  stated  in  Today
Homes and Infrastructure Pvt. Ltd. (supra) in paragraph 14 is only  relevant
and we find the legal  position  stated  therein  in  tune  with  the  ratio
decidendi laid down consistently by this Court in very many decisions.
The reliance was  also  placed  upon  the  decision  in  National  Insurance
Company Ltd. (supra). Paragraphs 19, 20 and 21 were referred to in the  said
judgment. Paragraph 19 can be usefully referred, which reads as under:

"19. In SBP & Co. v. Patel Engg. Ltd., a seven-Judge  Bench  of  this  Court
considered the scope of Section 11 of the Act and held that  the  scheme  of
Section 11 of the Act required the Chief Justice or his designate to  decide
whether there is an arbitration agreement in terms of Section 7 of  the  Act
before exercising  his  power  under  Section  11(6)  of  the  Act  and  its
implications. It was of the view that  sub-sections  (4),  (5)  and  (6)  of
Section 11 of the new Act, combined the power  vested  in  the  court  under
Sections 8 and 20 of the old Act (the Arbitration  Act,  1940).  This  Court
held: (SCC pp. 660-61 & 663, paras 39 & 47)
"39. It is necessary to define what exactly the  Chief  Justice,  approached
with an application under Section 11 of  the  Act,  is  to  decide  at  that
stage. Obviously, he has to  decide  his  own  jurisdiction  in  the  sense,
whether the party making the motion has approached the right High Court.  He
has to decide whether there is an arbitration agreement, as defined  in  the
Act and whether the person who has made the request before him, is  a  party
to such an agreement. It is necessary to indicate that he  can  also  decide
the question whether the claim was a dead one; or a long-barred  claim  that
was sought to be resurrected and whether  the  parties  have  concluded  the
transaction  by  recording  satisfaction  of   their   mutual   rights   and
obligations or by receiving the final payment without objection. It may  not
be possible at that stage, to decide whether  a  live  claim  made,  is  one
which comes within the  purview  of  the  arbitration  clause.  It  will  be
appropriate to leave that question to be decided by  the  Arbitral  Tribunal
on taking evidence, along with the merits of  the  claims  involved  in  the
arbitration. The Chief Justice has  to  decide  whether  the  applicant  has
satisfied the conditions for appointing an arbitrator  under  Section  11(6)
of the Act. For the purpose of taking  a  decision  on  these  aspects,  the
Chief Justice can  either  proceed  on  the  basis  of  affidavits  and  the
documents produced or take such evidence or get such evidence  recorded,  as
may be necessary. We think that adoption of this procedure  in  the  context
of the Act would best serve the purpose sought to be achieved by the Act  of
expediting the process of arbitration, without too many  approaches  to  the
court at various stages of the proceedings before the Arbitral Tribunal.
***
[pic]47. (iv) The Chief Justice or the Designated Judge will have the  right
to decide the preliminary aspects as indicated in the earlier part  of  this
judgment. These will be his own jurisdiction to entertain the  request,  the
existence of a valid arbitration agreement, the existence or otherwise of  a
live claim, the existence of the condition for the  exercise  of  his  power
and on the qualifications of the arbitrator or arbitrators."

Having gone through the said paragraphs, we do not find any position in  law
contrary to what has been stated in  Today  Homes  and  Infrastructure  Pvt.
Ltd. (supra), Reva Electrical Car Company Private Ltd. (supra)  and  Enercon
(India) Limited (supra).
Similarly, the reliance placed upon  in  Chloro  Controls  India  Pvt.  Ltd.
(supra) also does not in any manner dislodge the legal position relating  to
the stand alone Arbitration Clause in a substantive transaction recorded  in
writing. Therefore, we do not find any useful purpose by  referring  to  the
said decision as well.

Having thus  ascertained  the  legal  position  regarding  the  stand  alone
agreement relating to arbitration with particular reference  to  arbitration
agreement in a legal transaction between  the  parties,  when  we  refer  to
Clause 27 of the MoU, we wish to find out whether the said Clause  satisfies
the principles  set  down  and  applicable  to  a  stand  alone  Arbitration
Agreement. When we refer to Clause 27, we find that in the event of  failure
of an amicable settlement at the bilateral level relating to  a  dispute  or
difference arising between the appellant and the respondent  to  be  reached
as contained in Clause 26 of  the  MoU,  then  such  unresolved  dispute  or
difference concerning or arising from the MoU, its implementation breach  or
termination whatsoever  including  any  difference  or  dispute  as  to  the
interpretation of any of the terms of the  MoU  is  referable  to  the  sole
Arbitrator  appointed  by  the  appellant  and  the  respondent.  Therefore,
irrespective of the question or as to the fact whether  the  MoU  fructified
into a full-fledged agreement, having regard to the  non-fulfilment  of  any
of the conditions or failure of compliance of any requirement by  either  of
the parties stipulated in the other Clauses of MoU, specific  agreement  has
been entered into by the appellant and the respondent  under  Clause  27  to
refer such controversies as between the parties to the  sole  arbitrator  by
consensus. Therefore, when consensus was not reached as between the  parties
for making the reference, eventually it will  be  open  for  either  of  the
parties to invoke Section 11 of the  Act  and  seek  for  reference  of  the
dispute for arbitration.
In the case on hand, as we have noted earlier, after the signing of the  MoU
on 17.8.2007, the Board of Directors of the Respondent passed  a  Resolution
on 29.10.2007 which expressed its approval to the MoU, subject, however,  to
modification  of  the  conditions.  Thereafter,   correspondence   exchanged
between the parties from 17.12.2007 to 10.03.2010.  There was  a  subsequent
Board Resolution of the respondent  on  18.03.2010  which  stated  that  the
Board took a decision that it was not inclined to  extend  the  validity  of
proposed MoU due to change in the mineral policy of  the  State  Government.
However, on 26.07.2010,  the  respondent  informed  the  appellant  that  to
maintain parity, necessary modification in the terms and conditions  of  the
MoU dated 17.8.2007 was communicated to the State  Government  for  approval
which was awaited and that on receipt of such approval, a fresh MoU  can  be
executed. Thereafter,  by  communication  dated  25.4.2011,  the  respondent
categorically informed the appellant that it  decided  to  forthwith  cancel
the MoU dated 17.8.2007 alleging fault on the side  of  the  appellant  with
regard to failure to comply with the various terms  and  conditions  of  the
MoU.  Thus, from the above referred to sequence  of  events  which  occurred
between 17.8.2007 and 25.4.2011, it is crystal clear that both parties  were
at variance with reference to the various terms and conditions contained  in
the MoU and consequently there was every right in either of the  parties  to
seek for an amicable settlement  in  the  first  instance  as  specified  in
Clause 26 of the MoU.
We find from the materials on record that the appellant in its letter  dated
11.07.2011 addressed to respondent expressed its desire to amicably  resolve
the dispute at the bilateral level.  Since there was no  response  from  the
respondent, the appellant caused a legal notice on  07.12.2012  by  invoking
Clause 27 of the MoU for appointment of an  Arbitrator  and  also  suggested
the name of a retired High Court Judge and sought  for  the  concurrence  of
the respondent. In the legal notice, the  appellant  specifically  intimated
that in the event of the respondent failing to express its  concurrence  for
the appointment of the named Arbitrator, it will have no  other  option  but
to move the High Court under Section 11 of the Act.  The  respondent  having
made it clear in its reply dated 04.01.2013 to the lawyer's  notice  stating
that it was not inclined to agree for a  reference,  the  appellant  had  no
other option except to move the High Court by filing  an  application  under
Section 11 of the Act.
Having noted the above factors and inasmuch as we are convinced that  Clause
27 is a valid arbitration agreement contained in the  MoU  dated  17.8.2007,
the appellant was fully entitled to invoke the said agreement and  seek  for
a reference to the Arbitrator.
In the light of our above conclusion, we hold that the learned Judge  having
failed to appreciate the legal position  as  regards  the  existence  of  an
arbitration agreement in the MoU irrespective of the failure of the  parties
to reach a full-fledged agreement with respect  to  the  various  terms  and
conditions contained in the MoU for a joint  venture,  the  said  conclusion
and judgment of the  learned  Judge  is  liable  to  be  set  aside  and  is
accordingly  set   aside.   Since   the   respondent   has   expressed   its
disinclination to agree to express its concurrence and thereby  the  parties
failed to appoint an Arbitrator under the agreed procedure, it is  necessary
for this Court to appoint an Arbitrator. Therefore, while setting aside  the
judgment impugned in this appeal, we  hereby  appoint  Hon'ble  Ms.  Justice
Rekha Manharlal Doshit, resident of C-5,  402,  Deo  Sangam  Flat,  Guartgam
Road, Near Gandhi Nagar, Gujarat, former Chief Justice of Patna  High  Court
and former Judge of Gujarat High Court as the sole Arbitrator to  adjudicate
the disputes that  have  arisen  between  the  parties  on  such  terms  and
conditions as the sole Arbitrator deems fit  and  proper.  Undoubtedly,  the
learned sole Arbitrator shall decide all the disputes  arising  between  the
parties under the MoU, without being influenced by any prima  facie  opinion
expressed in this  order  with  regard  to  the  respective  claims  of  the
parties.
The Registry is directed to communicate this order to  the  sole  Arbitrator
to enable him  to  enter  upon  the  reference  and  decide  the  matter  as
expeditiously as possible.



The appeal stands allowed with the above directions.


                     .....................................................J.
                                          [Fakkir Mohamed Ibrahim Kalifulla]



                     .....................................................J.
                                                         [Shiva Kirti Singh]

New Delhi;
April 16, 2015

For the Latest Updates Join Now