Supreme Court of India (Single Judge)

Appeal (Civil), 22 of 2013, Judgment Date: Apr 07, 2015

                          IN THE SUPREME COURT OF INDIA
                           CIVIL ORIGINAL JURISDICTION

                         ARBITRATION CASE © NO.22 OF 2013

ONGC Petro Additions Limited                                        ..Applicant

                                        versus

Daelim Industrial Company Limited, Korea                       ..Non-applicant


                            J U D G M E N T


JAGDISH SINGH KHEHAR, J.


1.          In spite of the fact, that notice in this  case  was  issued  to
the non-applicant, and the non-applicant-Daelim Industrial Company  Limited,
Korea, was duly served, yet none entered appearance on behalf  of  the  non-
applicant. Even though the matter came to be adjourned  on  some  dates,  on
account of the absence of representation on  behalf  of  the  non-applicant,
under the belief that some one or the other would enter  appearance  on  its
behalf. The hope entertained by this Court was belied,  in the  sense,  that
none has entered appearance on behalf of the non-applicant.  Since the  non-
applicant was duly served, this Court is left  with  no  other  alternative,
but to proceed with the case against the non-applicant, ex-parte.
2.          We have heard learned counsel for the applicant.
3.           The  applicant  ONGC  Petro  Additions   Limited   (hereinafter
referred to as the 'OPaL') issued a notice inviting tenders, on  17.11.2009.
 By the aforesaid notice, the applicant solicited bids for  construction  of
a dedicated high density Poly Ethylene plant, for  its  Dahej  Petrochemical
Complex.  The pleadings in the present  arbitration  petition  reveal,  that
the non-applicant-Daelim Industrial Company Limited, Korea,  submitted   its
tender in response to the aforesaid notice on 17.11.2009. According  to  the
learned counsel representing OpaL, in terms of the  conditions  depicted  in
the notice inviting tenders, the bid documents submitted  by  the  tenderers
could be accepted by the  applicant  finally,  and  such  acceptance,  would
result in a concluded and binding contract.  Insofar as the  instant  aspect
of the matter is concerned, reference was made to Clause 26  of  the  notice
inviting tender dated 17.11.2009.  The same is being extracted hereunder:
“Clause 26 of the Instructions to the Bidder of the NIT dated 17.11.2009

26.0        Notification of Award:

26.1        Prior to the expiration of  the  period  of  Bid  Validity,  the
company shall notify the successful Bidder in writing by  registered  letter
or by fax or by telex that their tender has been accepted.

26.2        The above letter/ telex/ telefax of  acceptance  shall  construe
that the Contract shall be deemed to have been concluded.  The  Notification
of Award shall constitute a binding contract between the  successful  bidder
and the Company.”

                                       (emphasis is mine)


From a perusal of Clause 26.2, it clearly emerges, that  the  acceptance  of
the  bid  by  the  applicant,  would  by  itself,  conclude  the   contract.
Thereupon, the consequential 'notification of award', would be treated as  a
binding contract between the bidder and  the  applicant.   It  also  emerges
from the pleadings, that having accepted  the  bid  furnished  by  the  non-
applicant-Daelim Industrial Company Limited, Korea, the applicant  issued  a
'notification of award' on  6.1.2011.   According  to  the  learned  counsel
representing the applicant, the above notification demonstrates, the  factum
of a concluded contract between OPaL and the non-applicant;  whereby  Daelim
Industrial Company Limited, Korea, became bound by the bid submitted by  it,
in response to the notice inviting tenders.
4.          It is also necessary to reproduce  herein,  some  other  clauses
depicted in the  'notification  of  award'  dated  6.1.2011,  which  have  a
bearing on the determination of the present case. In this behalf, clauses  8
to 12 of the 'notification of award' are being extracted hereunder:
“8.0  M/S. Daelim Industrial Company  Ltd.  Shall  be  required  to  sign  a
formal Contract with Opal within 30 (thirty) days from the date of issue  of
this NOA.  This NOA shall constitute binding Contract  between  M/S.  Daelim
Industrial Company Ltd and Opal and  shall  be  subject  to  all  terms  and
conditions of the Biddings Documents and other documents mentioned  in  Para
1.0 above.

The date of commencement of activities under  this  Contract  shall  be  the
date of issuance of this NOA.

9.0 All other terms and conditions shall be  as  per  Bidding  document  No.
MR/OW/MM/HDPE/15/2009, subsequent Amendments and  Documents  issued  thereof
as mentioned at Para 1.0 above.

10.0 Kick off meeting shall  be  held  within  2  weeks  from  the  date  of
acceptance of this NOA.  Exact date/time and  venue  shall  be  communicated
shortly.

11.0 The effective date of Contract is the  date  of  this  Notification  of
Award i.e. 06.01.2011.

12.0 Kindly acknowledge this Notification of Award immediately.”

                                           (emphasis is mine)
A  perusal  of  clause  8.0  of  the  'notification  of  award',   extracted
hereinabove, reveals, that M/s Daelim  Industrial  Company  Limited,  Korea,
was required to sign a formal contract with OpaL within 30  days,  from  the
date of issue of 'notification of award'.  A perusal  of  the  same  clause,
further leads to the inference,  that  the  'notification  of  award'  would
constitute a binding contract between the applicant and  the  non-applicant,
and that, the terms and  conditions  expressed  in  the  bidding  documents,
would also constitute the conditions of the contract.   Furthermore,  clause
8.0 also  finalised  the  date  of  commencement  of  activities  under  the
contract, as the date of issuance of the 'notification of  award'.   Learned
counsel for the applicant also invited the Court's attention to clause  10.0
of the 'notification of award' dated 6.1.2011, which reveals, that the  kick
off meeting between the contracting parties would  be  convened  within  two
weeks from the date of acceptance of the 'notification of award' by the non-
applicant-Daelim Industrial Company Limited, Korea.
5.          In order to demonstrate the  conclusion  of  the  contract,  and
also the acceptance of the 'notification of award' dated  6.1.2011,  learned
counsel for the applicant invited this Court's attention to a  communication
dated 7.1.2011, addressed by  the  General  Manager  of  the  non-applicant-
Daelim Industrial Company Limited,  Korea.   An  extract  of  the  aforesaid
communication is being reproduced hereunder:
“Sub:-  Acknowledgment  of  Notification  Award  (NOA)  for  Dedicated  High
Destiny Poly Ethylene Plant (HDPE) for Dahej Petrochemical  Complex  against
Bidding Document No. MR/OW/MM/HDPE/15/2009

Dear Sir(s),

With reference to your Notification of Award (NOA) dated Jan. 6,  2011  (Ref
No. OPAL/BDA/CTS/089/10-11), as per the clause 12.0 of  the  foregoing  NOA,
we, Daelim Industrial Co., Ltd, are pleased to hereby acknowledge the NOA.

As for the Kick Off Meeting, we respectfully propose to invite you and  hold
the meeting in Daelim Seoul Office from Jan. 25, 2011 to Jan. 27, 2011.   We
would  like  you  to  kindly  confirm  the  proposed  meeting  schedule,  or
otherwise, inform us of your preferred date(s) and place for the meeting.

      Assuring you of our readiness to fulfill  all  your  requirements  for
this Project, we are  looking  forward  to  accentuate  our  competency  and
ability to provide you with success in this Project.

Faithfully yours,

Sd/-
S.Y. Lee
General Manager,
Daelim Industrial Co., Ltd.”

                                       (emphasis is mine)

Learned counsel for the applicant pointedly invited the  Court's  attention,
to the second paragraph of the aforesaid communication, and contended  that,
the non-applicant had requested for the convening of the 'kick off  meeting'
from 25.1.2011 to 27.1.2011.  It was the submission of the  learned  counsel
for the applicant, that the aforesaid 'kick off  meeting'  could  have  been
solicited by the non-applicant, only on the acceptance of the  'notification
of award' dated 6.1.2011 (as is clearly evident from clause 10 thereof).
6.          Learned  counsel  then  invited  this  Court's  attention  to  a
message, addressed by the non-applicant-Daelim Industrial  Company  Limited,
Korea, to the  applicant-OPaL  on  22.1.2011,  wherein  in  compliance  with
clause 3.3, the non-applicant submitted  a scanned copy of the  'performance
bank guarantee'.  The  aforesaid  message  dated  22.1.2011  is  also  being
extracted hereunder:
“Message

(Jinho Shin)shinjh@daelim.co.k  Sat, Jan 22, 2011 at 4.04 PM

To: sunilkumar upadhyay skuopal@gmail.com
Cc:”01(LESSY) Leesy@daelim.co.kr
(Park, Dong-Jib)”
djpark@daelim.co.kr,“01 (Dongkjh0907@daelim.co.kr,
jspark@daelim.co.kr

Dear Mr. Upadhyay,

As per the clause 3.3. “Performance  Guarantee”  in  General  Conditions  of
Contract, we hereby submit  our  scanned  “Performance  Bank  Guarantee”  as
enclosed.

The original copy is to be submitted in  the  contact  signing  ceremony  on
Jan.27, 2011.

Sincerely,
Jinho Shin
Jinho SHIN
Assistant Manager/Overseas Plant Business Team 1 DAELIM
17-7 Asiaone, Youngdungpo Ga, Yuido-Dong, Seoul, 150-010,
Korea.”

                                       (emphasis is mine)

Based on the communication dated 7.1.2011, and the message dated  22.1.2011,
learned counsel for the applicant contended, that  the  non-applicant-Daelim
Industrial Company Limited, Korea, had voluntarily  accepted  the  contract.
Based on the above acceptance, the terms  and  conditions  of  the  contract
were liable to be construed, in consonance with the 'notification of  award'
dated 6.1.2011, read along with the bid documents.
7.          There can be no doubt whatsoever, that the submissions  advanced
by the learned counsel for the applicant  deserve  acceptance,  even  though
the terms and conditions,  especially  clause  26  of  the  notice  inviting
tender dated 17.11.2009 reveals, that the acceptance  of  bid  documents  by
the applicant would constitute a concluded  contract  between  the  parties.
The communication dated 7.1.2011, and the  message  dated  22.1.2011,  fully
affirm the above conclusion.  The  two  communications  dated  7.1.2011  and
22.1.2011 leave no room for any doubt, that  the  non-applicant  consciously
accepted the 'notification of award'  dated  6.1.2011,  and  thereby,  bound
itself to the terms and conditions of the contract. .
8.           Despite  the  afore-stated  concluded  contract   between   the
parties,  it  seems,  that  the  non-applicant-Daelim   Industrial   Company
Limited,  Korea,  could  not  fulfill  its  obligations  in  terms  of   the
'notification of award'  dated 6.1.2011.  It is  therefore,  that  the  non-
applicant addressed a letter dated 11.2.2011 to the applicant,  wherein  the
non-applicant expressed its regret in not being in  a  position  to  execute
its  obligation,  under  the  contract.   The  letter  dated  11.2.2011   is
reproduced hereunder:
                                                    “Date: February 11, 2011
                                                                Ref: OBD-075

ONGC PETRO Additions LIMITED
VCCI Complex, 4th Floor, 73-GIDC Makarpura Road
Vandora -390010, India

Attention: Mr. Sunil Upadhyay, General manager (MM)- Opal.

Subject: Tender No.: MR/OW/MM/HDPE/15/2009 –  Dedicated  High  Destiny  Poly
Ethylene Plant (HDPE) for Dahej Petrochemical Complex at Dahej.

Dear Sirs,

Further to our email dated 8, 2011, we have been intensively discussed  with
the licensor, Chevron Philips Co., LP, in order to maintain our  partnership
established for a success in the subject project.

However, it is immensely regretful to inform  you  that  we  are  not  in  a
position to  enter  into  the  contract  since  we  failed  to  resolve  the
unsettled issues recently undergone with the licensor.

With much  gratitude  for  your  hospitality  towards  us,  we  respectfully
solicit your kind understanding for our situation.

Faithfully yours,
Sd/-
S.Y.Lee
General Manager
Daelim Industrial Co., Ltd.”
                                       (emphasis is mine)
9.          Consequent upon the default at the behest of the  non-applicant-
Daelim Industrial Company Limited,  Korea,  in  executing  the  contract  in
compliance with the 'notification of award' dated  6.1.2011,  the  applicant
issued a legal/arbitration notice, to  the  non-applicant-Daelim  Industrial
Company Limited, Korea. While indicating  the  obligations  which  the  non-
applicant had failed to fulfill, in consonance  with  the  'notification  of
award'  dated  6.1.2011,  the  legal/arbitration  notice  dated   26.11.2012
nominated Mr. Justice V.N. Khare, former Chief  Justice  of  India,  as  the
applicant's nominee arbitrator, for the resolution of  the  disputes  raised
in the legal/arbitration notice.  The  law  firm  (R.S.Prabhu  and  company)
which had issued  the  above  notice  dated  26.11.2012,  issued  a  further
communication to the non-applicant, on  behalf  of  the  applicant-OPaL  (in
continuation of the legal/arbitration notice dated 26.11.2012).  It  is  not
relevant, for the  purpose  of  disposal  of  the  present  controversy,  to
delineate the position depicted in the latter communication.
10.         In response to the  legal/arbitration  notice  dated  26.11.2012
(issued on behalf of the applicant), the non-applicant through its law  firm
(Kim and Chang) served a reply dated 21.1.2013.  Whilst denying  the  claims
raised by the applicant, against the non-applicant, as were set out  in  the
legal/arbitration notice dated 26.11.2012,  the  non-applicant  adopted  the
following expressed position in its reply:
“10.  In addition to  the  reservation  set  out  in  paragraph  5  of  this
Response, Respondent denies that the provisions of  the  Indian  Arbitration
and Conciliation Act, 1996 should apply to  this  arbitration  or  that  the
Chief Justice of India (or any person or institution designated by him)  has
the  authority  to  appoint  the  third  and  presiding  arbitrator  if  any
agreement cannot be reached between the party-appointed arbitrators.

11.   If an arbitration agreement does exist between the parties,  which  is
not admitted, the law and rule governing the procedure  of  any  arbitration
between the parties is the  Singapore  International  Arbitration  Act  (the
“Act”) and the UNICITRAL Rules respectively.

12.   Therefore, subject to the reservation set out in paragraph 5  of  this
Response and pursuant to Articles  7.1  and  9.1  of  the  UNICITRAL  Rules,
Respondent agrees to a three arbitrator arbitral tribunal and nominates  Mr.
Peter Leaver QC as its party appointed  arbitrator.   Mr.  Leaver's  details
are as follows:”

                                  (emphasis is mine)

A perusal of paragraph 10 of the reply issued by the law firm, on behalf  of
the non-applicant-Daelim Industrial Company Limited,  Korea,  would  reveal,
that the non-applicant denied the applicability of  the  provisions  of  the
Indian  Arbitration  and  Conciliation  Act,  1996.    In   fact,   it   was
specifically pointed out in paragraph  11  of  the  above  reply,  that  the
procedure for settlement of disputes  by  way  of  arbitration  between  the
parties, would be regulated as per the Singapore  International  Arbitration
Act, and in consonance with the UNICITRAL Rules. In paragraph 12,  the  non-
applicant agreed to an arbitral adjudication, by  a  three  member  arbitral
tribunal. It  is  therefore,  that  in  response  to  the  applicant  having
nominated Justice V.N. Khare,  former  Chief  Justice  of  India,  the  non-
applicant-Daelim Industrial Company  Limited,  Korea,  nominated  Mr.  Peter
Leaver, Q.C. to act as arbitrator on its behalf.
11.          It  is  not  a  matter  of  dispute,  that  the  two  nominated
arbitrators, were to appoint the presiding arbitrator,  by  mutual  consent.
Despite mutual consultations,  the  two  nominated  arbitrators,  could  not
arrive at a concensus on the  name  of  the  presiding  arbitrator.   It  is
therefore, that  the  applicant  approached  this  Court,  requiring  it  to
appoint the presiding arbitrator under Section 11  of  the  Arbitration  and
Conciliation Act, 1996.
12.         Before the prayer made at the behest  of  the  applicant,  under
Section 11 of the Arbitration and Conciliation Act, 1996,  is  accepted,  it
would be imperative for this Court to conclude, that the provisions  of  the
1996 Act are indeed applicable to the contract, executed between  the  rival
parties. It is therefore, that the Court required the  learned  counsel  for
the applicant, to respond to the objections raised by the law firm (Kim  and
Chang), through its communication dated 21.1.2013.
13.         In response, learned counsel  for  the  applicant  invited  this
Court's attention to clause 1.3 of the General Conditions of Contract (Part-
II) (as amended) of the notice inviting tender,  dated  17.11.2009.   Clause
1.3  relied  upon  by  the  learned  counsel  for  the  applicant  is  being
reproduced hereunder:
“1.3  Laws/Arbitration:

1.3.1       Applicable Laws

All  questions,  disputes  or  differences  arising  under,  out  of  or  in
connection with this Contract shall be settled in accordance  with  laws  of
India (both procedural and substantive) from time to time in  force  and  to
the  exclusive  jurisdiction  of  the  Courts  in  India,  subject  to   the
provisions of Clause 1.3.2.

1.3.2 Arbitration:

Except as otherwise provided elsewhere  in  the  contract  if  any  dispute,
difference, question or disagreement arises between the  parties  hereto  or
their respective representatives or assignees, at  any  time  in  connection
with construction, meaning, operation, effect, interpretation or out of  the
contract or breach  thereof  the  same  shall  be  decided  by  an  Arbitral
Tribunal consisting of three Arbitrators.   Each  party  shall  appoint  one
Arbitrator and Arbitrators so appoined shall appoint  the  third  Arbitrator
who will act as Presiding Arbitrator.

In case a party fails to appoint an  arbitrator  within  30  days  from  the
receipt of the request to do so by the other party or  the  two  Arbitrators
so appointed fail to agree on the appointment of third Arbitrator within  30
days from the date of their appointment, upon request of a party, the  Chief
Justice of India or any person or institution  designated  by  the  him  (in
case  of   International   Commercial   Arbitration)   shall   appoint   the
Arbitrators/ Presiding Arbitrator.   In  case  of  domestic  contracts,  the
Chief Justice of the High Court or any person or institution  designated  by
him within whose jurisdiction the subject  contract  has  been  made,  shall
appoint the arbitrator/ Presiding Arbitrator upon  request  of  one  of  the
parties.”

                                       (emphasis is mine)

      Having perused the notice inviting tender, dated 17.11.2009,  and  the
'notification of award' dated 6.1.2011, it is apparent, that the  terms  and
conditions in the notice inviting tender, were binding between the  parties.
 A perusal of clause 1.3.1 “applicable laws” leaves no room for  any  doubt,
for recording an effective conclusion, that the  parties  had  agreed,  that
all questions  or  disputes  arising  between  them,  would  be  settled  in
accordance with laws of India (both procedural and  substantive)  in  force,
from time  to  time.  Insofar  as  the  instant  aspect  of  the  matter  is
concerned, it is apparent, that the provisions  of  the  Indian  Arbitration
and Conciliation Act, 1996, lays  down  the  procedural,  as  well  as,  the
substantive provisions, relating to the settlement of arbitral  disputes  in
India.  It  is  therefore  not  possible  for  this  Court  to  accept,  the
objections raised by the non-applicant-Daelim  Industrial  Company  Limited,
Korea, in paragraph 10 of the reply filed on  behalf  of  the  non-applicant
through  its  law  firm,  expressing  that  the  provisions  of  the  Indian
Arbitration and Conciliation Act, 1996 would not apply to the settlement  of
disputes arising between the applicant  and  the  non-applicant.  Having  so
concluded, the assertion  made  by  the  law  firm  (representing  the  non-
applicant) in paragraph 11, to the effect that the parties  would  be  bound
by the provisions of the Singapore International Arbitration Act, is  liable
to be rejected, and is accordingly rejected.
      14.        It has already  been  recorded  hereinabove,  that  Justice
V.N. Khare, former Chief Justice of India, was nominated  as  arbitrator  on
behalf of the  applicant,  and  Mr.  Peter  Leaver  Q.C.  was  nominated  as
arbitrator on behalf of the non-applicant. In terms of clause 1.3.2. of  the
 General Conditions of  Contract  (Part-II)  (as  amended)  of  the  'notice
inviting tender' dated 17.11.2009, the arbitrators nominated  by  the  rival
parties, were to appoint the presiding arbitrator  by  mutual  consultation.
Insofar as the present controversy  is  concerned,  even  though  there  was
mutual consultation between the two nominated arbitrators, yet the same  did
not fructify into the appointment of an agreed presiding arbitrator.  It  is
in the above circumstances, that the applicant approached  this  Court,  for
appointing the   presiding  arbitrator,  under  Section  11  of  the  Indian
Arbitration and Conciliation Act, 1996.
      15.        Having arrived at the conclusion, that there was a  binding
contract between the parties, and further,  that  the  parties  were  to  be
governed by the provisions of the Indian Arbitration and  Conciliation  Act,
1996, there remains no room for any doubt, that in the absence of  consensus
between the nominated arbitrators, this Court  is  obliged  to  appoint  the
presiding arbitrator.  Accordingly, Mr. Justice  R.V.Raveendran,  a  retired
Judge of this Court, is appointed as the  presiding  arbitrator,  to  settle
the disputes raised by the applicant.
      16.        The presiding arbitrator shall be free to settle his  terms
and conditions of engagement.   He shall be forwarded a copy of this  order,
by the Registry of this Court, without any delay.  The presiding  arbitrator
shall commence proceedings of the arbitral tribunal comprising  of  himself,
Mr. Justice V.N. Khare and Mr. Peter Leaver Q.C., after consulting them,  at
the earliest.
      17.        It is necessary to record, that consequent upon  a  request
made by the non-applicant, it was  agreed  between  the  parties,  that  the
venue of the arbitral proceedings would  be  Singapore.  This  position  was
conceded by the learned  counsel  for  the  applicant.   It  is  accordingly
directed, that arbitral proceedings shall, subject to a mutual consensus  to
the contrary, be conducted  at Singapore.
      18.   Disposed of in the above terms.

                                                   …......................J.
                                                     [JAGDISH SINGH KHEHAR]

NEW DELHI;
APRIL 07, 2015.





ITEM NO.401               COURT NO.4               SECTION XVIA

               S U P R E M E  C O U R T  O F  I N D I A
                       RECORD OF PROCEEDINGS

Before Hon'ble Mr.Justice Jagdish Singh Khehar

Arbitration Case (Civil) No(s).22/2013

ONGC PETRO ADDITIONS LTD.                                       Applicant(s)
                                         VERSUS

DAELIM INDUSTRIAL COMPANY LTD. KOREA                        Non-Applicant(s)


Date : 07/04/2015 This petition was called on for hearing
   today.


For Petitioner(s)      Mr. Tushar Mehta, ASG
                       Mr. Rajat Nair, Adv.
                    for Mr. K. R. Sasiprabhu,AOR

For Respondent(s)

          UPON hearing the counsel the Court made the following
                             O R D E R

            The arbitration case (c) no.22 of 2013 is disposed of in terms
of the signed judgment.

                 Having arrived at the conclusion, that there was a  binding
contract between the parties, and further,  that  the  parties  were  to  be
governed by the provisions of the Indian Arbitration and  Conciliation  Act,
1996, there remains no room for any doubt, that in the absence of  consensus
between the nominated arbitrators, this Court  is  obliged  to  appoint  the
presiding arbitrator.  Accordingly, Mr. Justice  R.V.Raveendran,  a  retired
Judge of this Court, is appointed as the  presiding  arbitrator,  to  settle
the disputes raised by the applicant.

                 The presiding arbitrator shall be free to settle his  terms
and conditions of engagement.   He shall be forwarded a copy of this  order,
by the Registry of this Court, without any delay.  The presiding  arbitrator
shall commence proceedings of the arbitral tribunal comprising  of  himself,
Mr. Justice V.N. Khare and Mr. Peter Leaver Q.C., after consulting them,  at
the earliest.

            It is necessary to record, that consequent upon a  request  made
by the non-applicant, it was agreed between the parties, that the  venue  of
the arbitral proceedings would be Singapore. This position was  conceded  by
the learned counsel for the applicant.  It  is  accordingly  directed,  that
arbitral proceedings shall, subject to a mutual consensus to  the  contrary,
be conducted  at Singapore.

(Parveen Kr. Chawla)                                          (Renu Diwan)
    Court Master                                              Court Master
           
                   [Signed Judgment is placed on the file]

For the Latest Updates Join Now